How to track schedule slip: baseline vs current dates in a roadmap

Keep the first promised date next to the current one, so slip is something you can see.

Most roadmaps only know one date for each piece of work: the current one. When a target moves from March to April, someone edits the cell, and from that moment the plan says April as if it always had. Nobody lied. The plan just forgot.

Tracking schedule slip fixes that. You keep two dates side by side: the date you first committed to (the baseline) and the date you expect now (the current date). The gap between them is the slip. It sounds like bookkeeping, but it changes the conversations you have about the plan.

Why the original date matters

A plan with only current dates can look perfectly healthy while everything in it is late. Every item says “on track for its date”, because every date has been quietly redrawn. You find out at the deadline, which is the most expensive time to find out.

Keeping the baseline gives you three things the current date alone can't:

  • A size for the problem. “Launch is late” starts an argument. “Launch has moved three weeks since we agreed it” starts a plan.
  • A pattern over time. One slip is news. The same workstream slipping a week every fortnight is a signal that the estimate, the scope or the staffing is wrong.
  • Honest reporting. When you say something was delivered on time, you can say “on time against the date we committed to”, not against a date that was moved last Tuesday.

What to record

You don't need much. For each piece of work, keep:

  1. Baseline target date. The date you committed to when the work was agreed. Write it once and don't overwrite it.
  2. Current target date. The date you expect now. This one changes.
  3. Slip. Current minus baseline, in days or weeks. Positive means later, negative means it was pulled in.
  4. Each move, with a date and a reason. “12 Nov: +2 weeks, waiting on the supplier contract.” One line is enough.

The target date is the one to baseline. Start dates move too, and it's worth logging those moves, but a late start only matters if it pushes the finish. Keep the measure simple: one baseline per piece of work, on the date people are waiting for.

When to reset a baseline

A baseline is a promise, so it shouldn't move every time the work does. But it shouldn't be permanent either. If the scope genuinely changes, say the launch now includes a second market, the old baseline measures a different project. Holding the team to it makes the slip figure meaningless.

A workable rule:

  • Reset the baseline when the commitment changes: new scope, new agreed date.
  • Don't reset it because the work is late. Late is what the slip is there to show.
  • Keep the history when you reset, so you can still see what happened before.

If you find yourself resetting baselines every month, that's worth raising in its own right. Either the planning horizon is too long for the level of certainty you have, or commitments are being made before anyone knows enough to make them.

Showing slip so people actually see it

A slip column in a spreadsheet is a start, but it's easy to scroll past. Slip is most useful when it's visible on the plan itself, where people already look:

  • Colour by slip, not by team. Late in one colour, pulled in in another, on time in a third. Then a glance at the roadmap tells you where the trouble is.
  • Put the number on the bar. “+3w” next to a bar says more than a red bar alone, and it doesn't rely on anyone telling colours apart.
  • Mark the old dates. A small marker at each earlier target shows whether something slipped once, or keeps slipping.

Here's what that looks like. Drag the Launch target and watch the slip appear against its original date:

Research
Design
Build
Launch
Launch is due 17 Mar, on time.

Do this with your own plan, free

Doing it in a spreadsheet

If your roadmap is in a sheet, you can start today. Add a “Baseline target” column next to your target date, copy the current targets into it once, and then agree as a team that nobody edits that column without a reason recorded somewhere. Add a slip column with a simple formula (current minus baseline), and use conditional formatting to colour positive values.

The weak spot is discipline. Spreadsheets don't stop anyone overwriting the baseline, and they don't record each move unless someone writes it down. It works well for a small team with one owner. It starts to fray when several people edit the sheet, or when nobody remembers to log why a date changed.

Doing it in Plansies

This is the problem Plansies was built around. When you create a piece of work, its target date becomes the baseline automatically. Move the target later and the bar turns red, with the size of the slip shown next to it. Pull it in and it turns green. Each earlier target stays on the bar as a small marker, and every move is kept in the item's history. If the commitment genuinely changes, Reset baseline makes the current target the new baseline and keeps the history.

A short checklist

  • Every piece of work has a baseline target that doesn't get overwritten.
  • Slip is visible on the roadmap, not just in a column off to the side.
  • Each move has a date and a one-line reason.
  • Baselines are reset when the commitment changes, not when the work is late.
  • You review what moved regularly, rather than discovering it at the deadline.